MAIN-LINE AT JINJA REOPENS
Thursday, 19 June 2008

The main-line to Kampala from Kenya, closed near Jinja on 14 May following the collapse of an embankment due to a blocked culvert, was reopened to traffic on 16 June. During the four weeks that the line remained inoperable, freight was offloaded at Iganga and taken forward by road. According to Rift Valley Railways (RVR) project manager Glenn Kleyn, quoted by New Vision (published in Kampala) a new three-metre diameter galvanised iron culvert has been installed, to provide adequate outlet for stormwater to drain into Lake Victoria, about a kilometre downstream.

Kleyn said the repair work was being done at mile 323. In addition, the company is investigating a structure at mile 289 towards Busembatia.

"It (mile 289) is not in any immediate danger but we are investigating and drawing up designs," he told the paper.