Camrail confirms bridges suitable for planned bauxite tonnages

Posted: 13 Nov 2021, 08:42
by John Ashworth
Confirmation Of Rail Bridge Suitability For The 1 Billion Tonne Minim Martap Bauxite Project
Technical report from Camrail confirms all bridges on the Camrail rail line will be suitable for the planned tonnages for the Minim Martap Bauxite Project. The bridges are rated to a 20-tonne axle load, the rating required for the rail network to deliver greater than 5 million tonnes of bauxite per annum...