ELECTRIFICATION equipment inside the Severn Tunnel is deteriorating so quickly that trains may have to use diesel mode when running through the 6km structure.
At the moment, the switch from electric to diesel traction on down trains takes place at Bristol Parkway, but it had been hoped to complete electrification to Cardiff later this year.
However. it has emerged that recently-installed earthing straps connected to the overhead conductor rails inside the tunnel are already breaking down. Network Rail had estimated that they would be all right for 25 years...
The problems are due to the highly humid, saline atmosphere inside the tunnel. Pumps remove more than 60 million litres of water a day, which come from the ‘Great Spring’, and there are drainage tunnels under the main tunnel that take water to the pumps at Sudbrook, on the eastern side. Even so, conditions inside the tunnel are always unusually damp, no matter what the weather might be at either portal.
One immediate solution would be to use the diesel engines of the bi-mode Intercity Expresses when passing through the tunnel, but Network Rail has drafted in electrification specialists in a bid to find a longer-term remedy...
Damp Severn Tunnel has put electrification in doubt
Moderator: John Ashworth
- John Ashworth
- Site Admin
- Posts: 23606
- Joined: 24 Jan 2007, 14:38
- Location: Nairobi, Kenya
- Contact:
Damp Severn Tunnel has put electrification in doubt
Damp Severn Tunnel has put electrification in doubt